Section 2.3 • CBSE Class 11 Applied Mathematics

Exercise 2.3: Time and Work

Master the fundamental relationship between time spent and work completed, individual and combined unitary work rates, efficiency proportions, worker departure/arrival scenarios, and negative work in pipes and cisterns.

2.3 Time and Work: Fundamental Concepts

The physical or mental effort directed towards doing something refers to work. In simple mathematical language, work is an outcome of an effort applied for a particular time.

Direct Proportionality: Work is directly proportional to time ($\text{Work} \propto \text{Time}$). That is, more time given for work will increase the total work done.

If the amount of work (i.e. a task) remains constant, then two things play a vital role in determining the duration:
  1. Number of persons working
  2. Number of hours worked per day
Inverse Principle: In a task of constant magnitude, if the number of persons increases, the time required decreases, and vice versa.

Relation of Time and Work Done

To mathematically quantify time and work, we adopt the Unitary Rate Method where a complete job is treated as $1$ unit of work:

Let a complete piece of work be denoted by $W$.
  • If Ravi does work $W$ in $n$ days, then work done by Ravi in $1\text{ day} = \frac{1}{n}\text{ of } W = \frac{W}{n}$.
  • If Nitish does the same work $W$ in $m$ days, then work done by Nitish in $1\text{ day} = \frac{1}{m}\text{ of } W = \frac{W}{m}$.
  • If Ravi and Nitish work together and finish the entire work in $p$ days, then work finished by both in $1\text{ day} = \frac{1}{p}\text{ of } W$.
$$\text{Therefore, } \frac{W}{n} + \frac{W}{m} = \frac{W}{p}$$ Dividing both sides by $W$: $$\frac{1}{n} + \frac{1}{m} = \frac{1}{p} \quad \ldots(1)$$ Hence, the total number of days $p$ taken by both of them working together is: $$\mathbf{p = \frac{mn}{m + n}} \quad \ldots(2)$$
Generalization for Multiple Persons:
If $a$ persons work together for the same task taking $n_1, n_2, \dots, n_a$ days respectively, the combined rate becomes: $$\frac{1}{n_1} + \frac{1}{n_2} + \dots + \frac{1}{n_a} = \frac{1}{p}$$ where $n_a$ represents the number of days taken by the $a^{\text{th}}$ person alone.
Example 6 (CBSE Support Material)
Reena completes her canvas painting in 4 days. Mihir finishes the same canvas painting in 5 days. If they both work together, find out the number of days taken by them to finish it.
Step 1: Identify individual time spans:
Time taken by Reena alone ($m$) = $4\text{ days}$.
Time taken by Mihir alone ($n$) = $5\text{ days}$.

Step 2: Apply combined time formula:
$$\text{Number of days taken together } (p) = \frac{m \times n}{m + n} = \frac{4 \times 5}{4 + 5} = \frac{20}{9}\text{ days}$$ $$\mathbf{p = 2\frac{2}{9}\text{ days}}$$

Negative Work and Pipes & Cisterns

In practical problems, not all agents contribute towards completion. Some agents work against progress.

Definition of Negative Work:
If two objects or persons are working against each other due to which a delay or incompletion in task occurs, it is referred to as negative work.

Key convention:
  • Inlet pipe (filling tank) $\implies$ Positive Work Rate ($+\frac{1}{A}$)
  • Outlet pipe or leakage (emptying tank) $\implies$ Negative Work Rate ($-\frac{1}{B}$)
  • Net filling rate per hour: $\mathbf{\frac{1}{\text{Net Time}} = \frac{1}{\text{Inlet}} - \frac{1}{\text{Outlet}}}$
Example 7 (CBSE Support Material)
Pipe A can fill a tank in 20 hours. But due to a leakage it is taking thrice the time to fill the tank. If the tank is full, how long will it take to drain out the tank, if the pipe A is closed?
Solution:
Let the initial time taken by pipe A alone $= x\text{ hours}$ (given $x = 20\text{ hours}$).
Water filled by Pipe A in 1 hour $= \frac{1}{x} = \frac{1}{20}$.

After the leakage develops, the effective time taken to fill the tank becomes thrice $= 3x\text{ hours}$.
$\implies$ Net water filled in tank per hour with leakage $= \frac{1}{3x} = \frac{1}{60}$.

Let the full tank get emptied by the leak in $p$ hours.
Water drained out by leak in 1 hour $= \frac{1}{p}$.

$$\text{Net filling rate} = \text{Filling rate of Pipe A} - \text{Emptying rate of Leak}$$ $$\frac{1}{3x} = \frac{1}{x} - \frac{1}{p} \implies \frac{1}{p} = \frac{1}{x} - \frac{1}{3x} = \frac{2}{3x}$$ $$p = \frac{3x}{2}\text{ hours} = \frac{3}{2} \times 20 = \mathbf{30\text{ hours}}$$ Conclusion: The tank is completely drained out in 30 hours.

Work Efficiency and Man-Day Principles

1. Efficiency - Time Reciprocal Relationship:
Efficiency ($\eta$) is the rate of doing work per unit time.
$$\text{Efficiency} \propto \frac{1}{\text{Time taken}}$$ If Person A is $k$ times as efficient as Person B: $$\frac{\text{Efficiency of A}}{\text{Efficiency of B}} = \frac{k}{1} \implies \frac{\text{Time taken by A}}{\text{Time taken by B}} = \frac{1}{k}$$ $$\text{Time taken by A} = \frac{1}{k} \times \text{Time taken by B}$$
2. Chain Rule (Compound Proportion):
For a group of $M_1$ persons working $D_1$ days for $H_1$ hours each to produce $W_1$ work, and $M_2$ persons working $D_2$ days for $H_2$ hours to produce $W_2$ work: $$\mathbf{\frac{M_1 \times D_1 \times H_1}{W_1} = \frac{M_2 \times D_2 \times H_2}{W_2}}$$ When the work is identical ($W_1 = W_2$), the total person-hours are invariant: $$M_1 D_1 H_1 = M_2 D_2 H_2$$
Prev: 2.2 Calendar Chapter 2 Hub Next: 2.4 Speed, Distance & Time